Peoplecert MSP-Practitioner 시험요강:
| 주제 | 소개 |
|---|---|
| 주제 1 |
|
| 주제 2 |
|
| 주제 3 |
|
| 주제 4 |
|
| 주제 5 |
|
| 주제 6 |
|
| 주제 7 |
|
Peoplecert MSP-Practitioner 시험 개요:
| 인증 벤더: | PeopleCert (Axelos) |
|---|---|
| 시험명: | MSP Practitioner 5th Edition |
| 시험 번호: | MSP-Practitioner |
| 응시료: | USD 450-550 |
| 지원 언어: | 영어 |
| 자격증 유효 기간: | 3-5년 (PeopleCert 갱신 정책에 따름) |
| 시험 형식: | 객관식 테스트 시험지 (OTP), 시나리오 기반 문제, 객관식 |
| 관련 자격증: | MSP Foundation 5th Edition |
| 합격 점수: | 70% |
| 실제 시험 문항 수: | 70 |
| 시험 시간: | 150분 |
| 샘플 문제: | Peoplecert MSP-Practitioner 샘플 문제 |
| 응시 방법: | 온라인 감독관 시험 또는 공인 시험 센터 |
| 전제 조건: | MSP Foundation 5th Edition 시험 합격 필수 |
| 공식 요강 URL: | https://www.peoplecert.org |
최신 Peoplecert MSP MSP-Practitioner 무료샘플문제
문제 #1
Which of the following is Management document?
A. Programme brief
B. Project Dossier
C. Issue Register
D. Programme Mandate
문제 #2
Which of following is not a principal control for managing the tranches?
A. Business Case
B. Dependency management
C. Benefit Review
D. Business Case
문제 #3
The programme is in the 'deliver the capabilities' process in Tranche 3. Engineering staff have been installing the new water meters. As a result, fewer staff than planned have attended the first few training courses, delivered as part of the Training Project. If this trend continues, realization of the reduced costs could be delayed. The programme manager has asked the CEngO to schedule this routine work so that the engineers can attend training courses in the future.
Which theme is MOST relevant to this situation, and why?
A. Justification, because the delays to the training courses could impact how quickly the reduced costs are realized
B. Decisions, because the problem with the delayed training courses is causing a delay to delivery of the programme benefits
C. Justification, because further delays to the training courses will start to impact programme costs, affecting the business case
D. Decisions, because the programme manager is responding to possible delays to the training courses affecting programme benefits
문제 #4
The programme has just started. One outcome will be that fewer staff need to work as meter readers. The CEO of UU is keen to make the redundancy process as smooth as possible for the affected staff. As a result, the CEngO is attending a meeting with the meter readers to discuss UU's plans for the future, as well as the different redundancy and early retirement packages.
Is this an appropriate application of the 'lead with purpose' principle?
A. No, because the redundancies should not be discussed with affected staff until the Call Centre Rationalization Project has been started
B. Yes, because the CEngO should be able to explain to the meter readers what changes are being made and why
C. Yes, because this meeting should provide support to the meter readers and give them access to detailed information about the choices open to them
D. No, because the CEO has personal experience of being a meter reader and should attend the meeting instead of the CEngO
문제 #5
Which of following is not responsibility of Programme Office?
A. Risk and Issue tracking
B. Ensuring the control and management frameworks are effectively implemented
C. Repository of programme information
D. Providing regular updates on progress to SRO
질문과 대답:
| 문제 #1 정답: C | 문제 #2 정답: B | 문제 #3 정답: A | 문제 #4 정답: B | 문제 #5 정답: D |














1201 개 고객 리뷰
품질과 가치ITCertKR 의 높은 정확도를 보장하는 최고품질의 덤프는 IT인증시험에 대비하여 제작된것으로서 높은 적중율을 자랑하고 있습니다.
테스트 및 승인ITCertKR 의 덤프는 모두 엘리트한 전문가들이 실제시험문제를 분석하여 답을 작성한 만큼 시험문제의 적중률은 아주 높습니다.
쉽게 시험패스ITCertKR의 테스트 엔진을 사용하여 시험을 준비한다는것은 첫 번째 시도에서 인증시험 패스성공을 의미합니다.
주문하기전 체험ITCertKR의 각 제품은 무료 데모를 제공합니다. 구입하기로 결정하기 전에 덤프샘플문제로 덤프품질과 실용성을 검증할수 있습니다.