최신 Autodesk Certified Professional BIM_MGT_101 무료샘플문제:
1. The BIM manager receives an external lighting CAD file to link into the Architectural model and realizes the link is not vertically or horizontally aligned.
What fix needs to happen to resolve this misalignment?
A) The BIM manager needs to go to a 3D view and move the model to align with the architectural geometry.
B) The BIM manager needs to acquire the shared coordinates of the CAD file.
C) The Lighting team needs to add gridlines so the BIM manager can align its CAD file to the architectural gridlines.
D) The Lighting team needs to fix its shared coordinates to match those of the Architectural model and reissue the file.
2. A BIM manager is running clash detection for the first time on a large retail project during the Design Development phase. After copying all the models to the coordination space on Autodesk Forma, the matrix shows no clashes among any of the models.
How should the BIM manager proceed?
A) Continue forward on the project because there are no coordination issues.
B) Add sheets to the publish settings and rerun the clash.
C) Verify the shared coordinates for each model and republish.
D) Use the project as a case study for a firm-wide presentation.
3. An AEC company has received a design model from the Architect of Record to begin creating construction documentation. The BIM Execution Plan identifies a fast-track delivery schedule, and the project team includes new consultants with limited exposure to the client's preferred toolset and workflows. The BIM manager must determine how best to prepare the delivery team and assess the model's compatibility with internal systems.
As the BIM manager prepares for the Project Kickoff meeting, which two pieces of information are most critical to avoid issues related to digital compatibility? (Select two.)
A) Software version and build.
B) Graphic standards.
C) Any add-ins required.
D) Project units.
E) Shared Coordinates.
4. A BIM manager is creating a firm-wide template for mobilization plans to outline the key steps, resources, and strategies required to set up and launch BIM operations at the beginning of projects.
Which two components should the template include to accomplish the goal? (Select two.)
A) Common Data Environment.
B) Roles and responsibilities.
C) Project milestone dates.
D) Specifications.
E) Contract template.
5. What is included in a BIM Execution Plan?
A) Project schedule and design playbook.
B) LOD Matrix and project specifications.
C) Modeling standards and technology ecosystem.
D) Collaboration protocols and project playbook.
질문과 대답:
| 질문 # 1 정답: D | 질문 # 2 정답: C | 질문 # 3 정답: A,C | 질문 # 4 정답: A,B | 질문 # 5 정답: C |














0 개 고객 리뷰
품질과 가치ITCertKR 의 높은 정확도를 보장하는 최고품질의 덤프는 IT인증시험에 대비하여 제작된것으로서 높은 적중율을 자랑하고 있습니다.
테스트 및 승인ITCertKR 의 덤프는 모두 엘리트한 전문가들이 실제시험문제를 분석하여 답을 작성한 만큼 시험문제의 적중률은 아주 높습니다.
쉽게 시험패스ITCertKR의 테스트 엔진을 사용하여 시험을 준비한다는것은 첫 번째 시도에서 인증시험 패스성공을 의미합니다.
주문하기전 체험ITCertKR의 각 제품은 무료 데모를 제공합니다. 구입하기로 결정하기 전에 덤프샘플문제로 덤프품질과 실용성을 검증할수 있습니다.